I've just updated next months agenda to include Tickets #217 and #224. I am alerting you to this early so that you have sufficient time to review. Due to things on the Met office side we are not going to have CABLE fully active in JULES-5.6 release (October). We are still aiming towards JULES-5.7 though (February).
What is in our trunk now is almost the same as in HAC, ACCESS-CM2 and intended JAC. To make these exactly the same - such that only one version of CABLE exists, requires some further work. #217 and #224 are the first steps.
https://trac.nci.org.au/trac/cable/ticket/217 https://trac.nci.org.au/trac/cable/ticket/224
Following splitting up files (217), the modifications in HAC were included. The model was modified such that it was no longer bit reproducible. A full discussion is here https://accessdev.nci.org.au/p66/CABLE-HAC/cc6fdbc08cfcfef7c6f42ba499ec1b171853a342/notes.txt
Further investigation showed this first deviation from bitwise reproducibility was due to a trivial issue. Several plots are shown here: https://accessdev.nci.org.au/p66/CABLE-HAC/cc6fdbc08cfcfef7c6f42ba499ec1b171853a342/
These plots show that indeed there is no discernible to change to the model, which highlights the extreme sensitivity of the quantity surveyed in this respect, "new_sumbal".